Nationwide blackout looms as power generation drops below 3,000MW
Sadly, number of idle power plants increased to eight on Sunday from five on Friday.
It was gathered that a total generation stood at 2,886.7MW as of 6am on Monday, with seven power plants, including Sapele II and Alaoji II not generating any megawatt.
Other idle plants on Monday were Afam IV & V, Gbarain II, AES, ASCO and Rivers IPP, according to the latest data from the Federal Ministry of Power, Works and Housing.
At Afam IV & V, units GT1 to 12 have been de-commissioned and scrapped; GT13 to 16 are out on blade failure; GT17 and 18 out due to burnt generator transformer; and GT19 and 20 are awaiting major overhaul.
Sapele II’s GT1 unit was said to be out on undisclosed fault; GT2 tripped on low gas pressure; GT3 out on bearing lift pump trouble; and GT4 tripped on loss of auxiliary.
Gbarain II’s GT2 was said to be out for frequency management, while AES has been out of production since September 27, 2014.