Operation commences at Itakpe-Ajaokuta-Warri rail line June 2018 – Amaechi
The Minister made this known on Tuesday, while inspecting the ongoing rail project in Warri, Delta State.
The Minister said that, the project was first awarded in 1987 and abandoned for over 30 years, which would have been the first standard gauge in Africa.
He said, “There are two phases of the contracts; the first one was awarded in 1987. We have a directive from the federal government that we must complete the Itakpe-Ajaokuta-Warri rail line and it was put in this year budget.
“By the end of December last year, we had disbursed some money to the contractors; Julius Berger and others to commence work, so we have come to see how far.
“If this contract was completed within the time it was awarded, Nigeria would have been the first country in Africa to have a standard gauge line.
“We need to get this place functioning and the directive of the federal government is, we should start and our target is that by June, commercial activities will resume”.
The Minister explained that, “Julius Berger opted out of the project because it did not have equipment on ground after the Itakpe-Ajaokuta rail tracks was vandalised”.
Amaechi further disclosed that, Julius Berger would, however, handle the civil work to construct new yard, the 99 bridges, flyovers and refurbish the 178km yard in Agbor.
Inspecting the railway village in Agbor, the Minister ordered that the village with about 420 houses be handed back to the ministry, due to poor maintenance.
He said, the ministry would hand over the village to Julius Berger for total rehabilitation which could be rented to workers.
At the Abraka site, the Minister directed the Team Nigeria Ltd., the project consultant to expand the bridges to accommodate two vehicles as the bridgesconstructedcould only accommodate one vehicle.
However, Mr David Imafidon, Julius Berger Site Engineer, said that, with the level of work ongoing, the project could be completed within the speculated time.
He said that 99 bridges were to be constructed in the ongoing project with 12 rail stations to be constructed, adding that the overpasses to Agbor town were already completed.
Mr Chiedu Nwazojie, the Consultant of Team Nigeria Ltd. said that the company would make all the adjustment indicated by the minister to expand the bridges to accommodate more vehicles.
He said that the June 2018 date given to them by the minister was feasible.